Leschi's Marina Rebuild Is Running on the Grocery Store's Clock

October 29, 2026

Last May, Seattle Parks and Recreation began work at the Leschi South Marina and found that a corner grocery could stop it. In an update to its customers, Leschi Market said the city had received "over 900 emails regarding the impact on Leschi Market and surrounding businesses." Capitol Hill Seattle reported that the city then moved its contractors onto part of the parking lot and pushed major construction back until late summer.

The project resumed on September 14, but the plan was different. Parking limits, moved bus stops and planned night shifts now shape the work along Lakeside Avenue South, and nearly all of them trace back to the same goal: keeping the store at 103 Lakeside Ave open and easy to reach during business hours.

How 900 Emails Rewrote the Work Schedule

The work comes in two stages. Harkness Construction began the upland utility work on September 14, 2026. Parks expects it to take three to four months depending on weather, so the land-side work should finish somewhere between mid-December and mid-January. These utilities feed a new vessel sewage pump station that will be built in the water later in the project.

Some of that work has to happen on Lakeside Ave itself, and this is where the May pushback shows. The Seattle Parks project page, last updated October 20, says some of the street work will be done at night "to allow for parking and deliveries to occur at the Leschi Market during business hours." As of that update, Parks did not expect night work to begin until the end of October at the earliest. Shifts will start in the evening, with the loudest jobs, such as saw cutting and jackhammering, done before 10 p.m.

The night work will mainly affect the southbound lane. Where possible, northbound lane work will happen during the day, and the required curb ramps will be built in daylight hours. Parks says exact night-work dates depend on weather and progress, and it will announce them once they're set.

Where the Cars Go Now

The parking plan follows the same rule. The pier lot is closed. Most other spaces stay open, and the street spaces closest to the market now turn over faster. Parks estimates that about 200 parking spaces for the public, marina tenants and park users remain on parkland and the public right-of-way.

Area Before September 14 During construction
Pier parking lot, South Marina 39 park spaces Closed
Marina tenant strip, South Marina Open About 3 stalls nearest the pier closed
Public off-street strip, South Marina 21 spaces Open
Northbound parallel parking by the onland lot Open About 3 spaces nearest the pier closed, with short closures for deliveries
Lakeside Ave S south of Yesler Way Parallel parking 2-hour limit, added at community request
Leschi North Marina Tenant and park stalls No changes

The two-hour limit is the part to watch if you're used to leaving a car on Lakeside for a long lunch or an afternoon on the water. Signs mark the change.

Bus riders will also notice changes. On the southbound side near the South Marina, the stop has moved to mid-block for now. Between the two marinas, the northbound stop has moved to the north end of the block. Its old spot is now street parking or a load and unload zone, with one temporary accessible space.

Parks' posted parking plan covers September 14 through early November, weather permitting, so any changes for the next stretch of work will be posted on the project page. Questions go to Stephen Levengood at Seattle Parks at [email protected].

The Errands the Schedule Protects

The plan works around three businesses that make up most of the waterfront strip.

Leschi Market calls itself a full-service grocery that specializes in meat and wine. It carries produce, beer and more than 1,600 wines, and you can sign up on its site for notices about wine specials and tastings. The night shifts and the two-hour limit are built around it.

BluWater Bistro serves weekend brunch from 9 a.m. to 2 p.m. Its current menu includes hand-tossed pizzas and a harvest bowl with King salmon, Brussels sprouts, squash, quinoa and kale.

Daniel's Broiler Leschi runs happy hour from 3 to 5 p.m. daily, except holidays, according to its location page. Its menu centers on steak and seafood.

District 3 Councilmember Joy Hollingsworth has taken up the same point. In a constituent newsletter quoted by Capitol Hill Seattle on October 12, she wrote:

"I know major construction projects come with real pain points. Street closures, traffic changes, noise, access issues, and disruptions to small businesses can take a toll, and communication has not always been as clear or consistent as it should be."

Her office is pushing for "better coordination, earlier communication, and clear updates on detours and timelines," and the same update urges residents to keep visiting affected businesses.

What the Waterfront Gave Up for the Winter

Keeping the shops open came with a cost on the water. The old swim dock known as the Leschi Fire Dock is on its way out. The project calls for removing the existing timber pier and floating dock, and Capitol Hill Seattle marked the dock's final days on September 11, just before construction was set to begin, describing it as the marina's popular and "very old" swim dock. The paper reported that the plans don't say how the new setup will handle the Fire Dock's summer swim crowds. The name is still a mystery. According to city records cited in that story, the dock never served as moorage for the Seattle Fire Department's Lake Washington boats.

The cold-weather sauna is closed too. Bywater Sauna, which the Leschi Community Council welcomed to the marina last March, now lists its Leschi location on its website as "Currently closed due to nearby construction." Bywater's Madrona site, at Madrona Beach Park just south of the Spectrum Dance Theatre, is the closest one listed on its site.

Spring 2027, and the Street After That

The water-side work runs from September 2026 through spring 2027. Parks scheduled Manson Construction to arrive in late September or early October to remove large debris from under the South Marina, pieces too big for the dive team that did an earlier cleanup. Off-site fabrication of floats, piles and gangways was set to start in September. Parks expects no community impacts from the debris removal.

When it's finished, the creosote-treated timber dock and the old pipe pile breakwater will be replaced with a new public dock and a breakwater that actually protects the marina from waves. Parks says this part of Lake Washington has no public transient moorage or boat sewage pump-out today, and the current dock isn't accessible to people of all ages and abilities. The new facility will add the pump-out, moorage and some public seating. Capitol Hill Seattle reported that the plans also include benches and a kayak rack. Parks now lists the budget at $13.2 million, higher than the $7.9 million figure the paper reported this spring.

The market stays at the center of the next project too. The Leschi Community Council's October newsletter describes safety improvements on Lakeside Avenue between East Terrace Street and South Dearborn Street. The approved phase includes five sets of speed cushions and back-in angled parking by Leschi Market, with construction expected by the end of 2027. A further levy-funded phase is proposed for completion by the end of 2028.

Two Dates on the Leschi Calendar

The construction season still leaves time for neighborhood events. The Leschi Community Council has two on the calendar:

  1. Saturday, November 7: A planting party at the Leschi Natural Area, listed in the council's October newsletter.
  2. Wednesday, December 2, 7:00 to 8:15 p.m.: The Leschi winter potluck at Grace United Methodist Church, 722 30th Ave S.

If the utility work holds to Parks' three-to-four-month estimate, the potluck will fall shortly before the land-side crews are scheduled to wrap up on Lakeside.

Our family has worked along this shoreline since 1988, and a year when Lakeside Avenue changes block by block is when a neighbor who follows these details can help. If you're weighing a move to or from Leschi while the marina is rebuilt, Hinds Team can tell you what the construction schedule means for showings, parking and timing on your street. Contact Hinds Team whenever you're ready to talk it through.